Increasing Tho Xuan Airport capacity to meet 7 million passengers by 2050
(Chinhphu.vn) - According to the planning proposal, Tho Xuan Airport will add a 2th runway with a length of 3.800m, and simultaneously expand the terminal and aircraft apron to meet long-term operational needs.
The Civil Aviation Authority of Vietnam has just reported to the Ministry of Construction on the planning dossier for Tho Xuan International Airport for the period 2021-2030, with a vision to the year 2050.
Accordingly, based on the report of the Airports Corporation of Vietnam (ACV), the Civil Aviation Authority of Vietnam has collected professional comments from relevant agencies and units in the aviation sector. So far, ACV has acknowledged, explained, and completed the planning dossier according to the received comments.
After review, the specialized management agency assessed that the planning dossier was developed in close adherence to the planning tasks approved by the Ministry of Construction; it is consistent with the adjusted planning for the national airport system for the 2021-2030 period, with a vision to 2050, which was approved by the Minister of Construction in Decision No. 1140 dated 1/7/2026 and other relevant plans.
The dossier has analyzed and proposed a feasible planning scheme, meeting the development requirements of the airport for each planning phase; at the same time, fully acknowledging and explaining the opinions of relevant agencies and units.
Proposal to build a runway 3.800m long
According to the planning dossier, Tho Xuan International Airport is located in Sao Vang commune, Thanh Hoa province.
During the 2021-2030 period, the airport is planned to reach code 4E (according to ICAO standards) and level I military airport status.
The operational capacity is expected to reach 2 million passengers/year and 6.500 tons of cargo/year; it has sufficient capacity to operate aircraft types A320/A321, B747, B777 and equivalents.
Notably, during this period, the proposal file continues to use the existing runway (runway 1) with dimensions 3.200m x 50m; simultaneously, construct runway 2, with dimensions 3.800m x 45m, parallel to and approximately 360m away from runway 1 to the Northeast; each side has a material shoulder width of 7,5m.
The taxiway system is also proposed for synchronous investment, including 1 parallel taxiways located between two runways with a length of 4.100m; four rapid exit taxiways connecting runway 2 to the parallel taxiway; as well as connecting taxiways between runway 2 and the parallel taxiway, and between the parallel taxiway and runway 1.
The taxiways have a width of 23m, with material shoulders of 7,5m wide on each side, meeting the requirements for operating code E aircraft.
For the aircraft apron, it is planned to meet a capacity of about 2 million passengers/year, with about 11 code C parking positions or a combination of one code E position and 9 code C positions. The passenger terminal is also planned with a capacity of about 2 million passengers/year.
Vision 2050 reaches 7 million passengers/year
Vision to the year 2050, Tho Xuan International Airport is oriented to increase capacity to 7 million passengers/year and 23.000 tons of cargo/year.
According to the dossier, the runway and taxiway system remain unchanged as planned in the previous phase. The focus of infrastructure development in this phase is expanding the aircraft apron and passenger terminal to meet increasing operational demands.
Specifically, the aircraft apron is planned to be expanded to serve a capacity of 7 million passengers/year. The total number of aircraft parking positions is expected to be about 20 code C positions or a combination of 4 code E positions and 12 code C positions. The passenger terminal is also oriented to be expanded, increasing the operational capacity to about 7 million passengers/year.
According to the planning dossier, the total land use requirement for Tho Xuan International Airport during the 2021-2030 period, with a vision to 2050, is proposed to be nearly 845ha.
Implementing the regulations of Decree No. 205 dated 15/6/2026 of the Government regarding airports and airfields, the Civil Aviation Authority of Vietnam stated that it has submitted to the Ministry of Construction the dossier for collecting opinions on the detailed planning of Tho Xuan International Airport. This agency also proposed that the Ministry of Construction organize the collection of opinions from relevant ministries, branches, provincial-level People's Committees where the airport is located, and other relevant agencies and organizations according to regulations.
Based on the opinions received, the Civil Aviation Authority of Vietnam will coordinate with consulting units to study, incorporate, and finalize the detailed planning dossier for Tho Xuan International Airport, then submit it to the Ministry of Construction for appraisal and approval in accordance with regulations.
Tho Xuan International Airport (formerly known as Sao Vang military airport) is a dual-use (military and civil) airport located in Sao Vang town, Tho Xuan district, Thanh Hoa province. The airport is located approximately 45 km west of the center of Thanh Hoa city.
The airport currently has one runway with dimensions of 3.200m x 50m. The existing apron system meets about 6 aircraft parking positions at the same time. Passenger terminal T1 was put into civil operation in 2013 with a design capacity of about 1,2 million passengers/year.